Atascadero pavement rehabilitation project progresses 

pavement rehab

Signifigant work taking place on multiple streets in the coming weeks

– The City of Atascadero has announced that work on the 2022 F-14 Pavement Rehabilitation Project is progressing quickly. Over the next two to three weeks, significant work will be taking place on multiple streets as part of the project which may result in delays for residents. The city recommends planning additional time when leaving or returning home. For residents in areas surrounding the streets listed below, it is recommended to use alternative routes if possible.

The following are the construction activities taking place this week:

• Cenegal Road (Laurel Road to west): Roadway paving beginning Monday, continuing through Wednesday. Cenegal Road will remain open for residents, but paving operations will result in significant delays.

• Corriente Road (San Fernando Road to Santa Ana Road): Roadway paving beginning Wednesday, continuing through Thursday. The roadway will remain open for residents, but those not living on Corriente Road are asked to use alternate routes during paving operations.

• Balboa Road (San Fernando Road to Santa Ana Road): Roadway milling and base grading will commence Monday, continuing throughout the week. The contractor will provide traffic control, but delays of up to 20 minutes should be expected.

F-14 project improvements consist of pavement rehabilitation for a total of 3.3 miles of roadway, including Ardilla Road between Balboa Road and the northern end, Balboa Road between Santa Ana Road and San Fernando Road, Cebada Road between Santa Ana Road and the southern end, Cenegal Road between Laurel Road and the previous western terminus, and Corriente Road between San Fernando Road and Santa Ana Road. Additional improvements include upgrading existing CMP storm drain pipes and other minor drainage improvements. These improvements are funded through the F-14 Sales Tax Measure, which was passed by the community in 2014.

Changeable Message Boards (CMS) will be placed at visible locations on each roadway and will be kept updated with pertinent information regarding the schedule. During pavement rehabilitation, motorists are encouraged to pay close attention to the traffic signage and plan for extra time if travel through the area is necessary. Please drive carefully through the work zones and be considerate of both other drivers and workers. Large trucks, trailers, and recreational vehicles should use alternative routes where possible.

For more information or questions, contact Atascadero Public Works at (805) 470-3456 or [email protected].

For street project information, click on the following link: atascadero.org/index.phpoption=com_content&view=article&id=1134&Itemid=2174

About the author: News Staff

News staff of the A-Town Daily News wrote and edited this article from local contributors and press releases. Scott Brennan is the publisher of this newspaper and founder of Access Publishing. Connect with him on , Twitter, LinkedIn, or follow his blog. He can be reached at [email protected].

A-Town Daily News on Google
A-Town Daily News | 7343 El Camino Real #235 | Atascadero, CA 93422 | (805) 226-5720