City shares schedule of major downtown construction projects 

road closure

Projects are expected to impact traffic

– The City of Atascadero has multiple construction projects planned for 2023 within the downtown core area, including the 2023 F-14 Pavement Rehabilitation Project, the Downtown District Paving Project, and the Via Avenue Bridge Replacement Project. These projects are expected to impact traffic. Below is a schedule for the major projects impacting the downtown core.

The Via Avenue Bridge Project will be the first to commence, with the existing bridge scheduled for demolition in mid-June. During construction, which is anticipated to last until mid-November 2023, the bridge will be closed and through traffic will need to find an alternate route over Atascadero Creek.

The Downtown District Paving Project will commence in late-June, and last for approximately four months. The project contractor will be obligated to complete work on several of the roadways first, during school summer break, in order to minimize impacts on students’ families.

The 2023 F-14 Pavement Rehabilitation Project is scheduled to commence in late July and last approximately five months. Roadway treatments on both projects range from light resurfacing to full reconstruction, depending upon the current condition of the road.

These projects will result in a significantly safer and more comfortable driving experience. Residents and visitors to the downtown area should expect impacts to their typical travel routes from June through December 2023. In order to minimize these impacts to the greatest extent possible, the city will contract with a single construction manager to oversee and manage both paving projects.

Weekly updates will be provided throughout the remainder of 2023 so residents and visitors can anticipate and plan around scheduled road work. Click on the following link for project updates: https://www.atascadero.org/PublicWorks

 

 

About the author: News Staff

News staff of the A-Town Daily News wrote and edited this article from local contributors and press releases. Scott Brennan is the publisher of this newspaper and founder of Access Publishing. Connect with him on , Twitter, LinkedIn, or follow his blog. He can be reached at [email protected].

A-Town Daily News on Google
A-Town Daily News | 7343 El Camino Real #235 | Atascadero, CA 93422 | (805) 226-5720